Construction crews have completed 14 months of work at the future site of Simon Skjodt Assembly Hall.
Progress in May included East Corridor Terrazzo vitrification, completion of the north ADA slab, wood flooring replacement, and setting of the South Mechanical Room Air Handlers. Miscellaneous work still in process includes the mechanical, electrical, and plumbing installation, interior painting, Spirit of 76 Club concrete seating, acoustic cielings, and North Bleacher modifications. Also in progress is the high roofing, escalator pits, and the elevator.
This month, they will be fireproofing the balcony level, re-installing the North Bleachers, continuing to vitrificate the Terazzo, and completing the concession renovations. The upcoming milestones for this project include completing the concourse restrooms by July, and the punch list in August.